View Our Construction Photos
February 2010




October 2009
Aerial

Ambulance entrance

Healing Garden

Patient entrance
September 2009


March 2009

February 2009

Aerial photo. Photos show progress being made on Level 7, roof deck forming.

Placing and finishing concrete on Level 6 floor slab.

Level 7 (roof) formed, ready for concrete. View from upper parking lot looking south.

Hoisting final wall forms to pour the last of the structural shear walls between Level 7 and Level 8.
January 2009

January 16

Level 6 pour area 1. Laborers placing concrete on the deck via the pump truck and cement masons working to finish concrete. Wall and column forming will start the next day on this hardened concrete surface.

Progress photo showing Level 5 (ED) concrete decks fully poured and the forming of Level 6 (Nursing) in progress.

Large sanitary sewer system catch basin structure being set in place. Steel shoring box in place for safety and work performed on night shift to minimize impacts to hospital patients and traffic

January 7

Level 5 pour area 2 ready for concrete. Mechanical and electrical sleeving is in place along with reinforcing steel.

January 5th and still experiencing scattered snowfall. Overall the project was able to stay on the current schedule despite heavy snows through late December and the beginning of January.
November 2008

Aerial photo from November 1 showing footings complete, concrete columns and walls in progress working from south to north, and sub-grade preparation beginning for slab-on-grade activities.

Concrete pump truck placing concrete in the last shear wall to be finished on level 4. Now that all level 4 concrete walls and columns are placed, slab-on-grade activities will be the primary activity to get completed so that the level 5 concrete elevated slab can start to be formed.
Medical Staff Only

